Pre-Installation
4
PREPARATION OF THE INSTALLATION SITE
FREESTANDING INSTALLATIONS
As a base, build a platform or flooring in reinforced
concrete, at least 10 cm thick, perfectly flat and suitable
for supporting the weight of the bathtub and the people
using it.
The manufacturer suggests a minimum load of 350 kg/m
In any case contact a qualified construction engineer to
calculate the appropriate load for the installation site.
Wedges or shims cannot be placed under the bathtub
to level it, only the feet of the bathtub can be adjusted.
Remember to ground the structural reinforcement in
accordance with electrical codes.
Prepare:
A Drainage grating around the perimeter to help
•
preserve the equipment and the structure (even for
indoor installations).
See the plumbing and
electrical preparations on
page 15 and 23.
EN
B A non-slip flooring around the minipool.
•
For the preparation of the water and electrical
connections see the pertinent section on page 15
and 23.
.
2
Concrete slab h. 10 cm minimum, perfectly
level and able to support the weight of the
minipool + the weight of the people within
B
A
CONCRETE SLAB h. 10 cm min.
12
Fusion
minipool
Non-slip flooring
Drainage grating