Routing the AC
Note!
cables
-
-
IMPORTANT! The PE ground conductor of the AC cable must be laid in such a way that
it is the last to be disconnected in the event that the strain-relief device should fail.
This can be ensured, for example, by making it somewhat longer and by laying it in a
loop.
If AC cables are laid over the shaft of the DC main switch or across the connection block
of the DC main switch, they may be damaged when the inverter is swung in, or they may
even prevent the inverter from being swung in.
IMPORTANT! Do not lay AC cables over the shaft of the DC main switch or across the
connection block of the DC main switch.
Form loops with the AC cables when connecting them to the AC terminals.
When securing the AC cables using a metric screw joint, ensure that the loops do
not protrude beyond the connection area.
Otherwise, under certain circumstances it may no longer be possible to close the
inverter.
If overlength AC or DC cables are to be
laid in loops in the connection area, attach
the cables with cable ties to the eyelets
provided on the top and bottom of the con-
nection block.