3.1 PCS
PCS Parameter Table:
Parameter
DC voltage range
Maximum DC current
Rated AC voltage
Maximum AC current
Rated frequency
Maximum power
Maximum efficiency
Operating temperature
Dimension
Weight
GRID interface
LOAD interface
CT-Grid
CT-PV interface
DRM interface
DRM Function Explanation:
Value
84~216Vdc
40Adc
230Vdc
25Aac
50Hz
5kW
96%
-10~50℃
755*270*355mm
31kg
Connection to the grid, maximum current of
23.8A
Connection to the load, maximum current of
19.1A
Connection to the CT at the side of the
external power grid (the CT is the delivery
accessory)
Connection to the CT at the side of the
external PV inverter (the CT is the delivery
accessory)
Grid control interface, DRM0~DRM8
The Energy Pod is in the state of "Key-
DRM0
stop"
DRM1
The import power from the grid is 0.
The import power from the grid is no
DRM2
more than 50% of the rated power.
The import power from the grid is no
DRM3
more than 75% of the rated power.
The import power from the grid is no
more than 100% of the rated power.
DRM4
But subject to the constrains from other
active DRMs
DRM5
The export power from the grid is 0.
The export power from the grid is no
DRM6
more than 50% of the rated power.
The export power from the grid is no
DRM7
more than 75% of the rated power.
The export power from the grid is no
more than 100% of the rated power, but
DRM8
subject to the constrains from other
active DRMs.