Installation Ansi Installation Steps - GE EPM6000 Instruction Manual

Multi-function power meter
Hide thumbs Also See for EPM6000:

Advertisement

3.2
ANSI Installation Steps
EPM6000 MULTI-FUNCTION POWER METERING SYSTEM – USER GUIDE
1.
Insert 4 threaded rods by hand into the back of meter. Twist until secure.
2.
Slide ANSI 12 Mounting Gasket onto back of meter with rods in place.
3.
Slide meter with Mounting Gasket into panel.
4.
Secure from back of panel with lock washer and nut on each threaded rod.
Use a small wrench to tighten. Do not overtighten. The maximum installation
torque is 0.4 Newton-Meter.
NEMA12 mounting
gasket
threaded rods
lock washer
and nut
FIGURE 3–2: ANSI Mounting Procedure
CHAPTER 3: MECHANICAL INSTALLATIONANSI INSTALLATION STEPS
3–3