g – Vent Connection
✓With the return of the condensate, 10% flash steam is delivered to the condensate tank. If this
flash steam generation is not carried out of the condensate tank, it creates pressure in the tank
and causes deformation.
✓At the same time, the flash steam increases the condensate tank water temperature to very
high values, in which case overheated water will damage your feed pump. Therefore, the outlet
left as a vent on the condensate tank must be carried outside.
✓ Depending on the steam generator capacity, a port for the vent is left on the condensate tank.
✓The pipe diameter where the vent installation will be made should not be smaller than the
connection port diameter left on the condensate tank and must be the same diameter or above.
✓Vent connection should be made in such a way that the end is opened to outside environment
without being connected to any installation.
✓Do not use the condensate tank vent outlet for any installation connection.
h – Blowdown Connection
✓Steam generator and condensate tank blowdowns are combined and extended to the bottom
of the tank.
✓The assembly process that is required in place is to take the blowdowns left together to the
outside environment.
✓The blowdown installation must be made above the combined pipe diameter.
✓It should be remembered that for the vents made under pressure, small diameter pipes will not
be sufficient for evacuation.