8 Commissioning

8.1 Preparing Bluetooth Communication

8.1.1 Configuring the NetID on the Sunny Home Manager

Requirement for configuring NetID 1
For Bluetooth devices, NetID 1 is preset at the factory. You can only leave the NetID 1
configuration if your Bluetooth PV plant consists no more than one inverter and
one Sunny Home Manager.
• If the PV plant consists of more Bluetooth devices than one inverter and
one Sunny Home Manager, configure a different NetID as NetID 1.
• Use a screwdriver to turn the arrow of the rotary
switch to the NetID of the PV plant (blade width of
the screwdriver: 2.5 mm). For this purpose,
configure a NetID from 2 to 9 or A to F.
Installation Manual
8  Commissioning