3. Shorten unused insulated wires flush with the cable
sheath.
4. Strip approximately 6 mm of insulation off the
insulated wires.
5. Release the sockets of the four-pole plug with a
screwdriver and insert the insulated conductors into
pins 1 and 2 of the four-pole plug.
6. Write down the colour of the insulated wires.
7. Connect the four-pole plug to the connection socket
assigned to the given energy meter. For this
purpose, insert the four-pole plug into the lower pin
row:
• For consumption meters, insert the four-pole
plug into the connection socket "Meter 1".
• For feed-in meters, insert the four-pole plug into
the connection socket "Meter 2".
• For PV production meters, insert the four-pole
plug into the connection socket "Meter 3".
• For bidirectional meters for feed-in and purchased electricity, insert the connection plug of
the cable for purchased electricity into the connection socket "Meter 1". Insert the connection
plug of the cable for feed-in into the connection socket "Meter 2".
8. Connect the end of the cable to the energy meter. Observe the polarity of the insulated
conductors.
9. Use the labels provided to mark each cable with the connection socket and energy meter to
which it is assigned.
10. Note down the S0 pulses per kWh of each energy meter. This will facilitate meter configuration
in Sunny Portal.