Master Ups Installation Procedures - Toshiba G9000 Series Installation Manual

Sync kit
Hide thumbs Also See for G9000 Series:
Table of Contents

Advertisement

4

MASTER UPS Installation Procedures

CAUTION
4-1.
Install the fuse holder with 2 screws on the upper part of the panel inside bypass module.
4-2.
Insert three (3) fuses into the fuse holder.
4-3.
Affix the fuse label to the panel near the fuse holder.
4-4.
Connect the wire (Part# 3A) between the output bus bars (M4, the secondary side of 52S*)
and the fuse holder(M5). Refer to Figure 4-1 to Figure 4-3 for connection.
4-5.
Connect the field-installed wires (between MASTER and SLAVE UPS) to the fuse holder. Note: wires (qty. 3)
should have 600V insulation and be #16AWG, multi-strand, twisted trio with ring lugs sized for #12 screws.
6
1. Prior to the installation of the parts, confirm that the AC input breaker,
AC output breaker, Bypass input breaker and DC breaker are turned off.
(De-energize the interior of the UPS.)
2. Then remove the metal cover plates from UPS.
G9000 TOSHIBA SYNC KIT 1000-2000kVA Installation Manual - 200151-001