SLAVE UPS Installation Procedures

CAUTION
5-1. Install the fuse holder with 2 screws on the upper part of the panel inside bypass module.
5-2. Insert three (3) fuses into the fuse holder.
5-3. Stick the fuse label on the panel near the fuse holder.
5-4. Connect the wire (Part# 3B) between VSAU-48*(CN54) and the fuse holder(M5).
5-5. Connect the field-installed wires (between MASTER and SLAVE UPS) to the fuse holder. Note: wires (qty. 3)
should have 600V insulation and be #16AWG, multi-strand, twisted trio with ring lugs sized for #12 screws.
10
1. Prior to the installation of the parts, confirm that the AC input breaker,
AC output breaker, Bypass input breaker and DC breaker are turned off.
(De-energize the interior of the UPS.)
2. Then remove the metal cover plates from UPS.
Field-installed
wires from
MASTER UPS
Cable tie Mount
3xFuses,
Fuse holder
VSAU-48*
CN54

Figure 5-1: Installation procedures for SLAVE UPS(1000kVA)

G9000 TOSHIBA SYNC KIT 1000-2000kVA Installation Manual - 200151-001
Wires between
VSAU-48*(CN54)
and fuse holder(M5)
Color of wires
A-phase: Yellow
B-phase: Blue
C-phase: White
Upper part of bypass cabinet
The connection is for 1000kVA UPS.