Commissioning

6.7 Information pertaining to series commissioning

component replacement in plus and minus direction (+/-) with activated safety monitoring
function (SLS, if parameterized) in order to verify proper functionality.
6.7
Information pertaining to series commissioning
A commissioned project which has been uploaded to STARTER can be transferred to
another drive unit including the existing safety parameterization.
1. Download the STARTER project to the drive unit.
2. The alarms F01650/F30650 (acceptance test required) are output.
3. Click "Acknowledge hardware replacement" in the start screen of safety functions.
4. Backup all parameters to the CompactFlash card.
5. Perform a POWER ON at all components.
6. Before anyone is allowed to enter the danger zone again and before operation is
resumed, select the STO function once and briefly move the drives affected by the
component replacement in plus and minus direction (+/-) with activated safety monitoring
function (SLS, if parameterized) in order to verify proper functionality.
92
You can acknowledge these fault alarms as a complete acceptance test is not required if
no changes were made to safety function parameters.
Function Manual, (FHS) , 07/2007 Edition, 6SL3097-2AR00-0BP0