8. Connect the battery cables as below.
Battery connection cable (black)
Battery connection
cable (red)
Incorrect installation of batteries may damage the Fuse Unit or cause fire.
9. Insert Battery connection cable into the Cable guides as shown in the next diagram.
10. Install the Battery tray cover fitting to the three tabs and tighten the two screws.
Three tabs
Battery
connection cable
• Do not pull the Battery connection cable strongly.
• Be careful not to catch the Battery connection cable when installing the Battery
tray cover.
• Write down the year and month of the next battery replacement in the label
on Front cover.
Hardware Manual
Terminal
(black)
Terminal
(red)
< Front View >

Figure 2-33 Connecting the Battery Cables

Figure 2-34 Installation of Battery Tray Cover

Terminal
(black)
Terminal
(red)
Battery connection
cable (blue)
Two batteries
Two screws
(with stopper)
Battery tray cover
Cable guides