Gather Information

Gather Information
A successful job begins before the pull. The first step in planning is reviewing information already available
about the job and jobsite.

Review Job Plan

Review blueprints or other plans and make sure you have taken enlargement during pullback into account.
Check for information about existing or planned structures, elevations, or proposed work that may be
taking place at the same time.

Notify One-Call Services

Mark proposed path with white paint and have underground utilities located before working.
In the US or Canada, call 811 (US) or 888-258-0808 (US and Canada. Also contact any local utilities
that do not participate in the One-Call service.
In countries that do not have a One-Call service, contact all local utility companies to have
underground utilities located.

Examine Pullback Material

Ask for a sample of the new product material you will be pulling back. Check its weight and stiffness.
Contact the manufacturer for bend radius information. Check that you have appropriate pullback devices.

Arrange for Traffic Control

If working near a road or other traffic area, contact local authorities about safety procedures and
regulations.

Plan for Emergency Services

Have the telephone numbers for local emergency and medical facilities on hand. Check that you will have
access to a telephone.
32 - Prepare