4.12 System Power-Up Procedure

Use the following procedure as a power-up guide for Cougar and Jaguar
Switching Systems in order to bring the system in an orderly fashion.

Power-Up Guide

1. Apply power to the switching system control panels.
2. Apply power to the switching frames by connecting the AC power
cables to the AC line.
3. If installed, apply power to the external power supplies.
4. Apply power to the control system computers and wait for the boot-up
procedures to complete.
5. (Initial Power-Up Only) Install the Win3300 Control System according
to the directions found in the Win3300 Control System Manual.
6. (Initial Power-Up Only) Configure the Win3300 Control System accord-
ing to the directions found in the Win3300 Control System Manual.
7. Download the configuration to the 3300 Controller (installed in the first
video frame)
The switching system should now be ready for operation.