Figure 41. Version 2 Bypass Cabinet Bypass Ac Input Wiring - Eaton 9355 User Manual

10/15 kva
Hide thumbs Also See for 9355:
Table of Contents

Advertisement

UPS System Installation

Figure 41. Version 2 Bypass Cabinet Bypass AC Input Wiring

Line 1
Line 2
Line 3
20. Verify the phase rotation for each UPS and the bypass input.
21. Reinstall the internal cover.
22. Reinstall the bypass cabinet front cover.
23. Proceed to
4 4 . . 4 4
S S t t a a b b i i l l i i z z i i n n g g t t h h e e C C a a b b i i n n e e t t
NOTE 1
NOTE 2
To stabilize the cabinet(s):
1.
Lower the leveling feet to prevent the cabinet from rolling.
56
Eaton 9355 UPS (10/15 kVA) User's Guide 164201594—Rev H0
4.4 Stabilizing the Cabinet
to complete the UPS installation.
For seismic installations, you MUST order and install an Eaton 9355 UPS seismic kit; do
not use the following instructions.
For non-seismic installations, you MUST install the stabilizing bracket on all 3-high
cabinets. The stabilizing bracket is optional for 2-high cabinets.