Step 7: Installation is Complete

You have completed verifying the operability of your solution. Please proceed to Step 7.
If the Self Test does not pass for any of the instruments, the test indicates which module is likely to need ser-
vice. However, you should return all modules (except the M9300A) and all cables for that particular instru-
ment. All component modules for an M9381A or M9391A instrument are factory tested and calibrated as a
"bundle". It is important that you maintain the bundle when installing modules or returning an instrument for
repair.
To ensure that you send in the group of modules that
was reported in a Self Test failure, open the SFP and
go to Utilities > Calibration Options... to view this
screen.
The string pointed out in this image is the Cal ID. The
first 10 characters represent the Unique ID and the
remaining characters show the modules (and their
serial numbers) that constitute the M9381A or
M9391A instrument. A Certificate of Calibration for
that instrument contains the same information. Addi-
tionally, you may see this same information from the
SFP by using Help > About.
Step 7: Installation is Complete
Now that you have completed the installation and validated operation, you can proceed to:
32