Installing The Bollard - FAAC J275 2K HA Manual

Table of Contents

Advertisement

4.5 INSTALLING THE BOLLARD

!
Use a 1.5mm
2
16 core (15 + earth) cable for the electrical connec-
tions. Use a cable that complies with local regulations for use with
230 V~.
The maximum cable length is 50 m.
1. Place the cable inside the flexible sheath and make it protrude
from the pit by 1.6m.
2.  12 Fasten the cable to the frame using the cable gland pro-
vided 1 .
3. Insert the cable into the external junction box 3 through the cable
gland provided 2.
3
2
1
4. Connect the conductors to the external junction box and the
control board following the instructions in section § 5.1.
5. Check that the bollard operates correctly, according to the logics
set on the board, as well as all the accessories that are connected.
6. Remove the top cover 13 .
7. Screw the two M10 eyebolts, provided, onto the top of the frame
 1 4 .
8. Lift the bollard and insert it completely into the pit. 15. Position
the bollard so that the junction box is on the same side as the cable inlet.
!
Use belts or chains and a lifting device that are suitable for the weight
of the bollard.
Take care not to damage the electrical cable by pinching it between
the frame and the pit.