Test Setup and Results
4.8

Input Voltage Ripple

The TPS561201EVM-896 input voltage ripple is shown in
4.9

Start-Up

The TPS561201EVM-896 start-up waveform relative to V
The TPS561201EVM-896 start-up waveform relative to enable (EN) is shown in
resistive.
Figure 10. Start-Up Relative to Input Voltage
8
TPS561201EVM-896 1-A, SWIFT™ Regulator Evaluation Module
Figure 9. Input Voltage Ripple, I
Copyright © 2017, Texas Instruments Incorporated
Figure
9. The output current is as indicated.
= 1 A
OUT
is shown in
Figure
10. Load = 1.05 Ω resistive.
IN
Figure
Figure 11. Start-Up Relative to EN
Submit Documentation Feedback
www.ti.com
11. Load = 1.05 Ω
SLVUB34 – April 2017

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the SWIFT TPS561201EVM-896 1-A and is the answer not in the manual?

Subscribe to Our Youtube Channel

Table of Contents