Installation, connecting up, commissioning
5.3 Commissioning - procedure
Follow the steps outlined below:
1. Plugging in the CP:
Fit the CP onto the rack from the top and push it in at the bottom.
The CP can be operated in central or universal racks.
Note
K bus link
When using the universal rack UR1 or UR2 as an expansion rack, a communication bus
link is necessary!
2. Secure the CP with screws.
3. Turn on the power supply.
4. Connect the CP to Industrial Ethernet via one of the RJ45 jacks.
See also
Network settings (Page 42)
5.3
Commissioning - procedure
The steps for commissioning the CP are explained below. Commissioning involves the
addressing and downloading the configuration data and user programs.
Result: The CP is reachable in the network and has been supplied with configuration data.