Step 8. Install The Cables - Keysight N5232A Option 200 Installation Note

Add configurable test set and source attenuators upgrade kit
Table of Contents

Advertisement

Step 7.
Install the A29 and A30 Source Attenuator Assemblies
Refer to
Figure 2
for this step of the procedure. New parts are listed in
1. Install both source attenuator assemblies to the deck as shown, using two screws (0515-0372) with each
assembly. Use a T-10 TORX driver set to 9 in-lbs to tighten all screws.
Figure 2
Source Attenuators Installation
Step 8.
Install the Cables
Follow instructions carefully when making cable connections, especially wire harness
CAUTION
connections. Incorrect connections can destroy components, resulting in additional customer
costs.
Be careful not to damage the center pins of the semirigid cables. Some flexing of the cables
CAUTION
may be necessary but do not over-bend them.
Use a 5/16-in torque wrench set to 10 in-lbs on all cable connections except the front and rear
CAUTION
panel bulkhead connectors. On these, use a 9 mm nutsetter or open end torque wrench set to
21 in-lb.
Install the Semirigid Cables
To see an image showing the location of these cables, click the Chapter 6 bookmarks "Bottom RF Cables, 2-
Port Configuration, Option 216" in the PDF Service Guide
12
Table 1 on page
1
. New parts are listed in
Installation Note N5232-90101
7.
Table 1 on page
7.

Advertisement

Table of Contents
loading

Table of Contents