Install On Pole; Install On Wall; Connect Cable; Requirement For Cable Laying - Baicells mBS31001 Installation Manual

Lte tdd base station
Table of Contents

Advertisement

LTE TDD Base Station Installation Guide
3.5

Install on Wall

The wall must bear four times of the base station weight.
1.
Take apart the assembled installation bracket kit to get the installation bracket
2.
Fit the installation bracket on the wall, and mark the drilling locations.
Caution:
The arrow of the installation bracket must be upward.
3.
Drill two 10mm diameter and 70mm depth holes in the wall by following the
marked locations.
4.
Check the up/down direction of the installation rack, and then fix base station
to the wall using M8*80 expansion screws.
5.
Refer to the installation steps on pole, fix base station on wall.
3.6

Connect Cable

3.6.1 Requirement for Cable Laying

General requirements:
Bending radius requirement of feeder cable: 7/8" > 250mm, 4/5" > 380mm
Bending radius requirement of jumper cable: 1/4" > 35mm, 1/2" (super soft) > 50mm,
1/2" (ordinary)>127mm
Bending radius requirement of power cable and grounding cable: > tripled of the
diameter of cable
The minimum bend radius of the optical fiber is the 20 times of the diameter of
optical fiber.
Binding the cables according the type of the cable, the intertwining and crossing is
forbidden.
11