Eaton RLC1 Instructional Booklet page 13

O & m manual for the automatic transfer switch

Advertisement

O & M Manual for the RLC1
Automatic Transfer Switch
.
Figure 12. Cable Connection Locations (100 A).
UTILITY LUGS
GENERATOR LUGS
Figure 13. Cable Connection Locations (200 A).
IB01602016E
Step 2: The generator start terminals are located at the bottom of
UTILITY LUGS
GENERATOR
LUGS
Figure 14. Generator Start Terminals Location.
Step 3: Tighten all cables and wiring to specifications.
LOAD LUGS
4.5 Wiring
POWER CONDUCTORS AND CONTROL WIRING MAY HAVE VOLT-
AGE PRESENT THAT CAN CAUSE SEVERE PERSONAL INJURY OR
DEATH. DE-ENERGIZE ALL POWER OR CONTROL CIRCUIT CONDUC-
TORS BEFORE BEGINNING TO PERFORM ANY WIRING ACTIVITY TO
OR WITHIN THE ATS EQUIPMENT.
CHECK THE ATS EQUIPMENT NAMEPLATE AND THE ATC-100 FOR
RATED VOLTAGE. IT SHOULD BE THE SAME AS THE UTILITY AND
GENERATOR LINE VOLTAGES. OPERATING THE EQUIPMENT ON
IMPROPER VOLTAGE CAN CAUSE EQUIPMENT DAMAGE.
4.6 Installation
In a typical installation for critical loads (see Figure 15), the ATS
(1) and the generator (2) are connected to the power supply. The
ATS (1) and emergency distribution panel (3) receive utility power
from a dedicated breaker in the utility service panel (4). The ATS
and emergency panel receive generator power from the generator
(2). Power from the utility feeds the utility panel.
LOAD LUGS
For more information visit: www.eaton.com
Instructional Booklet
Effective: March 2014
the ATC-100 controller and are used when the generator
has an automatic start feature (see Figure 14). See Sec-
tion 4.9 for more detailed information on connecting the
generator start cables.
WARNING
CAUTION
Page 13
GENERATOR
START TERMINALS