2. Test Run Function

7-8. Test Run Function

Operates the unit with the thermostat forced ON.
(1)
Press and hold the
longer.
(2)
"
" appears on the remote controller LCD
display (Fig. 7-4).
(3)
Press the
The temperature cannot be adjusted in Test Run mode.
(This mode places a heavy load on the machines.
Therefore use it only when performing the test run.)
The test run can be performed using the HEAT, COOL,
or FAN operation modes.
The outdoor units will not operate for
approximately 3 minutes after the power
is turned ON and after operation is stopped.
If correct operation is not possible, an error code is
displayed on the remote controller LCD display.
(4)
Press the
To prevent continuous test runs, this remote controller includes a timer function that cancels the test run after
60 minutes.
The operation is possible even if the cassette-type ceiling panel has not been installed.
("P09" display does not occur.)
7
button for 4 seconds or
button to start the test run.
button to return to normal remote controller display.
(1)(4)
7-14
Remote Controller Functions
°
°
A
Fig. 7-4
(2)
(3)

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

U-200pe2e8aU-250pe2e8aS-250pe2e5

Table of Contents