3. Fix the four M5 cage nuts (
that the MBB should be installed at the rear of the rack. Please see Figure
18.
4. Use the four M5 screws (
).
7
5. Install the UPS Output Cover (
screws (
Scenario 2: The UPS, MBB and external battery pack need to be installed
on the rack. For such application, the UPS and external battery pack must be
installed at the front of the rack, the MBB at the rear of the rack (see Figure 19
and Figure 20), and the total height is 4U (see Figure 19).
External
Battery
Pack
UPS
5
). Please see Figure 18.
6
External Battery Pack
UPS
× 1 PC
1
MBB
× 2 PCS
× 2 PCS
5
4
× 2 PCS
7
Chapter 8
) at the two sides of the rack. Please note
7
) to secure the MBB on the rack's M5 cage nuts (
) at the back of the UPS with two #6-32
3
BATTERY PACK
ESC
(Figure 19)
MBB
× 2 PCS
4
(Figure 20)
2 1
How to Install the Maintenance
Bypass Box on the Rack
Height :
4U
× 1 PC
3
× 2 PCS
6
× 2 PCS
5
× 2 PCS
7
× 1 PC
1
External
Battery
Pack
UPS