Connection of Factory Pre-Terminated HVSC Plus (Upper End) to
Stormaster ESE Terminal
Tools required for the installation of the factory completed upper termination include:
∆
Sharp knife
∆
PH2 Phillips head screw driver
∆
3 mm Hex/Allen Key
1. Firstly remove the protective packaging from the cable and upper terminated end section
taking care not to cut cable or associated upper termination parts in the process.
2. Using a Phillips Head screwdriver, remove the M6 Phillips Head screw holding the mast butt
adaptor (if fitted) to the lower connector and retain both screw and mast butt adaptor.
3. Feed the HVSC Plus cable through the FRP support mast.
4. Slide the black plastic mast butt adaptor back onto the lower finial connector, line up
holes and screw the Phillips Head screw into position tightly. Now screw the mast butt
adaptor into the Stormaster ESE terminal and tighten the M6 Grub screw at the base of the
terminal to lock the assembly.
Figure 32.
Labelling
Warning labels are supplied with all Stormaster ESE terminals and should be installed as per
the following.
∆
In locations where personnel may be in close proximity to the HVSC Plus downconductor
∆
Where the HVSC Plus downconductor connects to the earthing system
∆
At the base of the support mast
There are 2 warning labels supplied in the front cover of this manual and also 2 supplied in the
lower termination kit. If more labels are required, contact your nearest LPI supplier or distributor.
Masts
The mast chosen for the application must:
∆
Raise the terminal to a height of at least 2 metres higher than the structure