Install On Wall; Connect Cable; Requirement For Cable Laying - Baicells Nova-233 G2 Installation Manual

Outdoor lte tdd base station
Hide thumbs Also See for Nova-233 G2:
Table of Contents

Advertisement

3.5

Install on Wall

The wall must bear four times of the base station's weight.
1.
Take apart the assembled installation bracket kit to get the installation bracket.
2.
Fit the bracket on the wall, and mark the drilling locations.
Caution:
The arrow of the installation bracket must be upward.
3.
Drill two 10mm diameter and 70mm depth holes in the wall on the marked
locations, and insert the expansion pipes.
4.
Check the up/down direction of the installation rack, and then fix base station
to the wall with M8 x 80 expansion bolts.
5.
Refer to the installation steps on pole, fix base station on wall.
3.6

Connect Cable

3.6.1 Requirement for Cable Laying

General requirements:
Bending radius requirement of feeder cable: 7/8" > 250mm, 4/5" > 380mm.
Bending radius requirement of jumper cable: 1/4" > 35mm, 1/2" (super soft) > 50mm,
1/2" (ordinary)>127mm.
Bending radius requirement of power cable and grounding cable: > tripled of the
diameter of cable.
The minimum bend radius of the optical fiber is the 20 times of the diameter of
optical fiber.
Binding the cables according the type of the cable, the intertwining and crossing is
forbidden.