Mechanical installation
3.2 Mechanical installation: Checklist
Table 3- 1
Mechanical installation: Checklist
Item
Activity
1
The ambient conditions must be permissible.
(→ See general technical data in section "System data" in chapter "System overview")
2
The load-carrying capacity and properties of the ground must fulfill the requirements
for installation of the Cabinet Modules.
(→ See the chapter titled "Cabinet Modules" in the technical data for the relevant
Cabinet Modules)
3
The crane transport assembly (option M90) installed for delivery must be removed
once the transport unit or individual cabinet units have been set down at the final
installation location.
(→ See the section below titled "Mechanical installation", subsection "Disassembling
the crane transport assembly")
4
Before the cabinet units are finally installed, the wooden pallets supplied with the
transport unit must be removed properly.
5
The minimum ceiling height required (for unhindered air discharge) must be observed.
The cooling air supply and exhaust must not be obstructed and must be available in
sufficient quantity.
(→ See the section below titled "Mechanical installation", subsection "Preparatory
steps")
6
The cabinet must be firmly attached to the fixing points provided.
A proper connection must be established if the cabinet units are installed side-by-side.
(→ See the section below titled "Mechanical installation", subsection "Connection for
side-by-side installation of cabinet units")
7
The following optional components, which are supplied separately for transport
reasons, must be assembled by the customer. This applies to the following options:
IP21 degree of protection with canopy (option M21)
IP23/IP43/IP54 degrees of protection with hood or filter elements
(options M23, M43, M54)
8
If it is possible to enter the area underneath the cabinet units, plant-side shock
protection must be provided for this area.
9
The handle must be mounted for option L37 (DC interface including pre-charging input
circuit).
(→ See the chapter titled "Options", subsection "DC interface including pre-charging
input circuit")
10
With option M26, the installed cabinet equipment must be enclosed on the right, and
with option M27, the installed cabinet equipment must be enclosed on the left.
Side panel installed on the right (option M26)
Side panel installed on the left (option M27)
11
All shock protection measures (guards, plates) in and on the cabinet units must be
installed before commissioning.
12
The clearance around an open door (escape route) specified in the applicable
accident prevention guidelines must be observed.
36
Applicable?/Completed?
S120 Cabinet Modules Equipment Manual
Manual, (GH5), 10/2008, A5E00427098A

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Sinamics s120 cabinet module

Table of Contents