Advertisement

5. Connect the racks, using M10 hardware through holes in the sides (―SCREW M10 X 25mm,‖ ―M10 FLAT
WASHER‖ and ―NUT M10‖). Torque the bolts to 30Nm (22 ft lbs).
6. After all the rack frames are anchored, reattach the side panels to the outermost rack frames using four M5
Screws (―SCREW M5 X 10 mm‖) for each side panel. Fasten the screws using torque of 5.1–6.1 Nm (45–54 in lbs).
ET003222373
English 4/2018. Rev 0.0

Figure 3-6: Rack Anchoring Points (4 EA)

Figure 3-7: Holes on the sides of the rack

Figure 3-8: Reattaching the Side Panels

.