Outdoor Unit - Carrier 42QHP09E8S Service Manual

Oasis plus 3d inverter series
Hide thumbs Also See for 42QHP09E8S:
Table of Contents

Advertisement

1.3.2

Outdoor Unit

Evacuation for the whole system
Procedure:
1.
Confirm that the 2- and 3-way valves are opened.
2.
Connect the vacuum pump to the 3-way valve's
service port.
3.
Evacuate the system for approximately one hour.
Confirm that the compound meter indicates
-0.1 MPa (14.5Psi).
4.
Close the valve (Low side) on the charge set and turn
off the vacuum pump.
Wait for five minutes then check whether the gauge
needle moves after turning off the vacuum pump. If
the gauge needle moves backward, check whether
there is gas leakage.
5.
Disconnect the charge hose from the vacuum pump.
6.
Mount the caps of service port and 2- and 3-way
valves.
7.
Use a torque wrench to tighten the caps to a torque
of 18N.m.
Page 25