Option #5 - Cycles
You can use this option to set all the stations in a certain Program/start to repeat their cycles. For example, this
option allows you to run a group of stations several times a day to keep a newly seeded area moist.
Select the Program/Start you want to set repeating cycles for. Then, when you select option #5, the display
shows:
P1 T1 Cycles <1>
Number 1 indicates normal programmed operation. You can enter any number up to 9, but be aware that if you
enter a zero, the stations in that Program/start will repeat continuously until stopped by a programmed End time, a
programmed skip day, or a manual OFF.
Press the number key for the number of repetitions you want. In this example, the display shows the
cycle will repeat five times:
Completes the option setting. The display shows:
Exits the function, restores the time display.
Option #6 - Cycle Delay
This option sets the length of time between repetitions, or cycles, in a cycle Program (see Option #5).
Select the Program and Start you want to set the cycle delay for. Then, when you select option #6, the display
shows:
The maximum delay time you can Program is 24 hours.
Note: The time mode (M or S) is dependent on the setting of Option #3. To change modes, see Option #3.
Completes the option setting. The display shows:
24
P1 T1 Cycles= 5
P1 T1 Cycles= 5
Press the number keys for the length of time you want between repetitions of the watering
cycle. In this example, the display shows a 30-minute delay from the end of one cycle to
the beginning of another:
Cycle Dly <off>
Cycle Dly 0:30M
Cycle Dly= 0:30M