7.
Click Download Data to LevelMaster.
8.
Click OK when finished.
9.
Select the Monitor tab to verify that the temperature and tank level readings are being displayed. Floats can be moved to
ensure readings reflect and update float position as expected. Ensure the temperature reading is as expected.
10. Disconnect the laptop from the board.
11. Reinstall the unit back into the tank as described in section 8.5, Reinstall the unit into the tank
12. Restore field wiring as described in section 8.3, Restore field wiring.
13. If required, calibrate the unit as described in section 7, Calibration from the host controller.

Move a LevelMaster from one tank to another

The following procedure will describe how to prepare and remove the LevelMaster from one tank and install it into another tank.
Installing a LevelMaster from another tank is similar to a first-time installation. Wiring and new conduits may be required
depending on the location of the new tank and the distance from the flow computer, remote controller or barrier board. When
planning the installation of a LevelMaster that has been in operation in another tank determine the following:
Verify that the length of unit is the same as required for the new tank.
Verify that the existing float(s) type is the appropriate for the liquid being measured in the new tank.
Determine the basic setup for the unit: ID, baud rate, etc.
Determine if the unit will be the only unit on the site.
If connecting to additonal units on a RS-485 bus, determine if the unit is an intermediate or the last unit on the bus.
Use the MasterLink software package to run a test which will establish new offsets to match the LevelMaster to its new
surroundings.
DANGER - Serious damage to health/risk to life. When performing service or using a laptop in a classified area,
ensure explosive gasses are not present.
Tool required:
Phillips screwdriver
To move a LevelMaster from one tank to another:
1.
Remove the power and cover as described in section 8.1, Remove the enclosure cover.
2.
Remove field wiring as described in section 8.2, Remove field wiring.
3.
Reinsert cover for safe handling of the unit.
4.
Remove the unit from the tank as described in section 8.4, Remove the unit from the tank.
5.
Remove enclosure cover again.
6.
Connect to the unit as described in section 8.8, Establish local communication with electronics board.
7.
Configure the unit as required for the new location.
8.
Reinstall the enclosure cover.
9.
Insert the unit into the new tank as described in section 8.5, Reinstall the unit into the tank.
10. Wire the unit as required. Wiring the unit in the new tank is the same as if it was being installed for the first time. Review
section 4, Wiring, to use applicable procedures.
11. If connecting to a Totalflow flow computer or remote controller, verify measurement readings and ensure that no errors are
displayed in the LevelMaster application (PCCU). See section 6.5, Verify basic configuration.