Comissioning guide

Advertisement

Calibration of feed dose - Auger version
Controller setup
Press anywhere on the display and then press the OPE-
RATION icon.
Operation settings menu:
Use the + and - buttons together with OK and the Return
key to navigate the menu system.
- Confirm that burner is set to OFF.
Feeder menu:
Enter the FEEDER SETTINGS menu.
Change the pellets diameter to 6 or 8 mm. pellets.
Calibration of feed dose with a auger fed boiler:
If the boiler is attached to a external feeding auger the start dose value needs to be veriefied ac-
cording to the below information.
Remove the black plastic hose which connects the feeding auger with the burner unit. Place
some sort of container underneath the plastic hose to collect the pellets that will be fed during a
auger filling procedure.
The hole down the fall shaft to the burner (where the black plastic hose where connected origi-
nally) needs to plugged temporarily in order to be able to build under pressure in the fire box and
allow the auger to feed in test mode.
Enter the OPERATION menu and then INSTALLATION menu. Activate the FILL FEEDER function
which will force feed pellets for 15 minutes. Meanwhile the auger is filling up tap the auger repea-
tedly to ensure that it is packed with fuel. When pellets comes out at the end of the auger the fill
feeder should be set back to NO and then directly back to ON to have a full 15 minutes feed of
pellets to make sure enough pellets is in the auger. Collect the pellets in a bag or container during
this 15 minute feed. Do not stop the feeding process, it is critical to have a properly packed and
filled auger in order to calibrate the feed rate in the next step.
A correctly adjusted start dose is one of the most critical and important steps of a
comissioning process. If the start dose is incorrect it will give the wrong output on the
boiler which might create operational issues, excessive wear on parts and even be
dangerous in extreme situations.
8
Effecta AB - Västra Rågdalsvägen 21 - 434 99 Kungsbacka - 0300 - 22320 - info@effecta.se
Operation settings
Burner
Fan
Feeder settings
Temperature set
Information
Service
Installation
VER: 3.0
Feeder settings
Start dose
Support dose
Pellets diameter
Run start dose
Run supp. dose
Run oper. dose
Off
50s
10s
6
No
No
No