Download Print this page

Effecta Komplett III 25kW Quick Start Manual page 15

Comissioning guide

Advertisement

Calibration of feed dose - Suction version
Setting the start dose
When the auger is properly packed and filled enter the
OPERATION menu and open the FEEDER SETTINGS
menu and then press RUN START DOSE.
Collect the pellets being fed during the test start dose
process. It should be exactly 40cl. If it is less increase the
amount of seconds of the start dose and run another test
It the start dose is greater than 40cl decrease the amount
of seconds for the start dose and then run the test start
dose again.
Keep testing until the start dose being fed is exactly 40cl.
When this step has been processed the boiler is to be
reassembled again by putting the fall shaft hose back in
to the burner.
NOTE: A good value to begin with is 48s for the start
dose. It will take the initial tests close to 40cl. of feed
rate.
The elbow connecting the fall shaft with
the on board storage. Remove it by un-
winding the two M8 nuts.
If the feeder isn´t running it is likely that under pressure over the boiler isn´t sufficient.
Make sure that the burner fall shaft is plugged at all time when the black plastic fall
hose is out of the burner.
Effecta AB - Västra Rågdalsvägen 21 - 434 99 Kungsbacka - 0300 - 22320 - info@effecta.se
Operation settings
Burner
Fan
Feeder settings
Temperature set
Information
Service
Installation
VER: 3.0
Feeder settings
Start dose
Support dose
Pellets diameter
Run start dose
Run supp. dose
Run oper. dose
Off
48s
10s
6
No
No
No
15

Advertisement

loading

This manual is also suitable for:

Komplett iii 35kwKomplett iii 20kw