5.2 BOX INSTALLATION PROCEDURE
Dig a hole big enough to hold the box
containing the operator.
Insert the tubes for water drainage in the
prepared holes (A) Insert the sheath for laying
the power cables and limit switch (B).
Note: while positioning the box, keep in
mind the minimum distance there must be
between the pillar and the centre of rotation
of the gate hinge.
Cement so that the box cannot be moved,
wait for it to dry and then assemble the
operator and levers.