6.4

Checking the electrical connection

After the sauna control device and the sensor are electrically connected the following
points should be checked:
7

Commissioning

7.1

Safety instructions

Electric
potential
Installation instructions Sauna control Series FCU2x00/FCU3x00/FCU4x00 / Version V 2.18
Does the voltage supply match the specifications on the nameplate?
Have the cable specifications given in Table 1, page 9 and the electrical circuit
diagram Figure 17, page 28 been followed?
Is the control device connected according to the electrical circuit diagram?
Are the sensors (temperature and humidity) connected as per section 5.6, page 18
ff?
DANGER!
Danger to life due to electric potential!
Contact with live components can be fatal.
Damage of the insulation of the individual components can be
dangerous to life.
Therefore:
For switching off the mains, the power supply cable must be equipped
with a fuse with a contact opening width corresponding to the
requirements of the excess voltage category III for total
disconnection.
Disconnect the unit from the mains before carrying out any work on it
(switch off the fuse in the distribution box) and secure against
restarting. Check for zero potential. The control device should be
disconnected from the mains before opening the casing.
In case of damage to the insulation, switch off the power supply
immediately and carry out the repair.
Work on electrical unit should be carried out by certified electricians
only.
Never bypass fuses or put them out of operation.
While replacing fuses, pay attention to correct current specifications.
Keep moisture away from live components, since it can lead to short
circuit.
WARNING!
If a short circuit occurs in a 230V/400V load, the relay contact can
be welded by the high short-circuit current. Is turned on before
removing the short circuit, the safety relay can be also welded.
This can lead to the continuous operation of the load. Turn off the
circuit breaker in the junction box. Send the unit back to the
factory for check/repair.
Commissioning