9 Configuration of the Inverter

9 Configuration of the Inverter

9.1

Starting the Installation Assistant

The installation assistant leads you step-by-step through the steps necessary for the initial configuration of the inverter.
Layout of the installation assistant
A
C
Figure 25: Layout of the installation assistant (example)
Position
Designation
A
Configuration steps
B
User information
C
Configuration field
Requirement:
☐ Without the SMA Grid Guard code settings for the utility grid are only possible within the first ten operating hours
(see "Measured Values and Parameters" at www.SMA-Solar.com) After completion of the first ten operating
hours, the SMA Grid Guard code must be available (see "Application for SMA Grid Guard Code" at www.SMA-
Solar.com).
Procedure:
1. Activate the user interface (see Section 8.1, page 110).
2. Log in as Installer.
3. Select the menu User Settings (see Section 8.3, page 114) on the start page of the user interface.
4. In the context menu, select [Start the installation assistant].
☑ The installation assistant will open.
118
SI44M-80H-12-BE-en-10
Description
Overview of the installation assistant steps. The number of steps de-
pends on the type of device and the additionally installed modules.
The current step is highlighted in blue.
Information about the current configuration step and the setting op-
tions of the configuration step.
You can make settings in this field.
SMA Solar Technology AG
B
Operating Manual

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Sunny island 8.0hSunny island 6.0h

Table of Contents