Manual Switching Tests

Manual Switching Tests
............................................................................................................................................................................................................................................................
Description
Main OLIU Switch Test
...........................................................................................................................................................................................................................................................
365-372-304
Issue 7, March 2003
This test will initiate switching commands from the CIT TL1
Command Builder and verify proper switching and LED indications.
Important!
previous tests.
Use the scroll bar in the
Step 1
the
rtrv-state-path
............................................................................................................................................................................
Click on the
Step 2
............................................................................................................................................................................
Step 3
Click
Send
Result:
followed by a
Ring 1 or Ring 2 is the active ring.
The M1 OLIU is associated with Ring 1 and the M2 OLIU is associated
with Ring 2.
............................................................................................................................................................................
Use the scroll bar in the
Step 4
the
opr-protnsw-sts1
............................................................................................................................................................................
Click on the
Step 5
............................................................................................................................................................................
If the active ring is Ring 2, change the
Step 6
under the
<STS1PROTN>
1
between the brackets
Select Man (manual) to operate a manual switch.
............................................................................................................................................................................
Click
Step 7
Send
Result:
followed by a
Lucent Technologies - Proprietary
See notice on first page
An STS1 cross-connect should still exist from the
Command Builder
command.
command.
rtrv-state-path
to issue the command.
The Response Window should display the command
indication as well as indicating whether
COMPLD
Command Builder
command.
command.
opr-protnsw-sts1
column to
{ }
and selecting
to issue the command.
The Response Window should display the command
indication.
COMPLD
Operational Tests
window to scroll down to
window to scroll down to
parameter listed
m{1}-1-{1}
by double clicking on
m{2}-1-{1}
2
from the drop down window.
7 - 1 3

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the Metropolis and is the answer not in the manual?

Subscribe to Our Youtube Channel

Table of Contents