Parts; Vigv Bushing Inspection Schedule - GE MS-6001B Maintenance Instructions Manual

Gas turbines with dln-1 combustion systems gas only
Hide thumbs Also See for MS-6001B:
Table of Contents

Advertisement

Introduction
Frame Size
VIGV
MS5001, 5002, 6001 403 Stainless Steel 158A7888, P004,5,6
MS5001, 5002, 6001 403 Stainless Steel 315A9681 or 339A9913
MS5001, 5002, 6001 GTD 450
MS7001, 9001
403 Stainless Steel
403 Stainless Steel
GTD 450

Parts

GE Power Systems maintains a large volume of replacement parts to cover the requirements of gas tur-
bine owners. The parts protection system is designed for rapid response; however, there are periods of
heavy demand where certain parts may not be readily available for planned inspections.
It is strongly recommended that high probability parts be available on site prior to the start of inspections.
Spare and Renewal Parts sales personnel have responsibility for customer contact, to advise scheduling
of maintenance parts and identify additional parts needs. Local Spare and Renewal Parts sales personnel
can present operations spare parts recommendations and factor individual needs into gas turbine mainte-
nance philosophy as well as to provide for planned maintenance parts, including time tables and making
suitable recommendations concerning design improvements and modifications to improve reliability,
maintainability or reduce operating cost. In addition gas turbine parts programs such as interchangeabil-
ity, exchange plan, warehousing program, and repair and return policy can be identified.
I–6
Table 1-1. VIGV Bushing Inspection Schedule
Bushing
315A9681 or 339A9913
158A7888
315A9681 (or 339A9913)
315A9681 or 339A9913
Inspection and Maintenance
Clearance Limits
Inspection
for Bushing
Changeout ( inches)
0.050
0.050
0.075
0.070
0.070
0.100
Interval
(Hours)
5,000
8,000
16,000
8,000
8,000
16,000