Major Inspection — Disassembly Procedures
4. Unbolt and remove the top half of the number two bearing exhaust baffle.
5. Unbolt and remove the bearing strap and upper half bearing liner.
6. Cover the open bearing housing to protect the rotor bearing journal.
7. Wrap the removed liner for protection, identify and tag all parts for reassembly.
Operation 18 — Perform Hot Gas Path Disassembly Operations 18 and 19
Note: Refer to the Hot Gas Path Inspection section, in this Service Manual for
the following disassembly operations.
1. Remove upper half second and third stage nozzle radial retaining pins.
2. Remove upper half second and third stage nozzle segments.
MI-D-26