THE FORCE/1
Operational Guidelines (Sidewalls), Cont
If clogging or less than satisfactory compaction occurs, adjust the slide
gate inward by
1
inch increments until the situation clears. If the
2
problem doesn't clear, add an additional 50 feet of 2 inch hose and
readjust your machine settings.
Insert the insulation nozzle into the lower hole of the wall cavity. Turn
blower switch "on" first, then the agitator. When the sidewall is full, the
FORCE/1 blower will rev up, trying to work harder and material flow
may stop. Turning "off" first the agitator, then the blower keeps the
material from clogging the outlet hose. Allow the blower to completely
stop before removing the nozzle from the hole. Repeat the procedure
using top hole until wall cavity is full.
Caution: If you are inexperienced with blowing sidewalls you may
loosen or blow off sheetrock, or you may accidentally fill areas such as
closets.