Section 3 Starting Up; Factory And Site Acceptance Testing; Commissioning Checklist - ABB REC650 Commissioning Manual

Relion 650 series bay control
Hide thumbs Also See for REC650:
Table of Contents

Advertisement

1MRK 511 248-UEN -
Section 3
3.1
3.2
Commissioning Manual
Starting up

Factory and site acceptance testing

Testing the proper IED operation is carried out at different occasions, for example:
Acceptance testing
Commissioning testing
Maintenance testing
This manual describes the workflow and the steps to carry out the commissioning
testing.
Factory acceptance testing (FAT) is typically done to verify that the IED and
configuration meets the requirements by the utility or industry. This test is the most
complex and in depth, as it is done to familiarize the user to a new protection or to
verify a new configuration. The complexity of this testing depends on several factors.
New IED type
New configuration
Pre-configured
Modified existing configuration
Site acceptance testing (SAT or commissioning testing) is typically done to verify
that the new installed IED is correctly set and connected to the power system. SAT
requires that the acceptance testing has been performed and that the application
configuration is verified.
Maintenance testing is a periodical verification that the IED is healthy and has
correct settings depending on changes in the power system. There are also other
types of maintenance testing.

Commissioning checklist

Before starting up commissioning at site, check that the following items are available.
Single line diagram
Protection block diagram
Circuit diagram
Setting list and configuration
RJ-45 Ethernet cable (CAT 5)
Three-phase test kit or other test equipment depending on the complexity of
the configuration and functions to be tested.