Section 6
Testing functionality
6.3.9.2
6.3.10
6.3.10.1
56

Completing the test

Continue to test another function or end the testing by setting the parameter
TestMode to Off under Main menu/Tests/IED test mode/1:TESTMODE. If
another function is tested, then set the parameter Blocked to No under Main menu/
Tests/Function test modes/Current/CCRPLD(52PD)/X:CCRPLD for the
function, or for each individual function in a chain, to be tested next. Remember to
set the parameter Blocked to Yes, for each individual function that has been tested.

Broken conductor check BRCPTOC

Prepare the IED for verification of settings as outlined in
verify
settings".
Values of the logical signals for BRCPTOC are available on the local HMI under
Main menu/Tests/Function status/Current/BRCPTOC(46,lub)/X:BRCPTOC.
The Signal Monitoring in PCM600 shows the same signals that are available on the
local HMI.

Measuring the operate and time limit of set values

1.
Check that the input logical signal BLOCK to the BRCPTOC function block
is logical zero and note on the local HMI that the output signal TRIP from the
BRCPTOC function block is equal to the logical 0.
2.
Set the measured current (fault current) in one phase to about 110% of the set
operating current IP>.
Observe to not exceed the maximum permitted overloading of the current
circuits in the terminal.
3.
Switch on the fault current and measure the operating time of BRCPTOC.
TRIP is controlled by Gate 13 in the configuration.
Use the TRIP signal from the configured binary output to stop the timer.
4.
Compare the measured time with the set value tOper.
5.
Activate the BLOCK binary input.
6.
Switch on the fault current (110% of the setting) and wait longer than the set
value tOper.
No TRIP signal should appear.
7.
Switch off the fault current.
8.
Set the measured current (fault current) in same phase to about 90% of the set
operating current IP>. Switch off the current.
9.
Switch on the fault current and wait longer than the set value tOper.
No TRIP signal should appear.
10. Switch off the fault current.