1MRK 514 027-UEN D
Section 1
1.1

This manual

The installation manual contains instructions on how to install the IED. The manual provides
procedures for mechanical and electrical installation. The chapters are organized in the
chronological order in which the IED should be installed.
1.1.1

Presumptions for Technical Data

The technical data stated in this document are only valid under the following circumstances:
1.
Main current transformers with 1 A or 2 A secondary rating are wired to the IED 1 A rated
CT inputs.
2.
Main current transformer with 5 A secondary rating are wired to the IED 5 A rated CT
inputs.
3.
CT and VT ratios in the IED are set in accordance with the associated main instrument
transformers. Note that for functions which measure an analogue signal which do not
have corresponding primary quantity the 1:1 ratio shall be set for the used analogue inputs
on the IED. Example of such functions are: HZPDIF, ROTIPHIZ and STTIPHIZ.
4.
Parameter
5.
Parameter
phase voltage.
6.
Parameter
7.
The rated secondary quantities have the following values:
8.
For operate and reset time testing, the default setting values of the function are used if
not explicitly stated otherwise.
9.
During testing, signals with rated frequency have been injected if not explicitly stated
otherwise.
1.2

Intended audience

This manual addresses the personnel responsible for installing the product hardware.
The installation personnel must have basic knowledge of handling electronic equipment.
650 series
Installation manual

Introduction

IBase used by the tested function is set equal to the rated CT primary current.
UBase used by the tested function is set equal to the rated primary phase-to-
SBase used by the tested function is set equal to:
IBase × UBase
√3 ×
Rated secondary phase current I
Rated secondary phase-to-phase voltage U
Rated secondary power for three-phase system S
© Copyright 2017 ABB. All rights reserved
is either 1 A or 5 A depending on selected TRM.
r
is within the range from 100 V to 120 V.
r
= √3 × U
r
Section 1
Introduction
GUID-AB423A30-13C2-46AF-B7FE-A73BB425EB5F v19
GUID-1E949E38-E04D-4374-A086-912C25E9F93C v2
× I
r
r
GUID-C9B8127F-5748-4BEA-9E4F-CC762FE28A3A v11
5

Advertisement

Table of Contents
loading

This manual is also suitable for:

Relion 650 series

Table of Contents