SETTING GUIDELINES
Following changes on the network caused by faults or other operational requirements, it is possible that various
subsystems will be formed within the power network. It is likely that these subsystems will suffer from a
generation/load imbalance. The "islands" where generation exceeds the existing load will be subject to
overfrequency conditions. Severe over frequency conditions may be unacceptable to many industrial loads, since
running speeds of motors will be affected. The overfrequency element can be suitably set to sense this
contingency.