Commissioning; Creating The Drive Project Offline - Siemens SINAMICS S120 Getting Started

Hide thumbs Also See for SINAMICS S120:
Table of Contents

Advertisement

Prerequisites
2.4

Commissioning

Once you have carried out the steps described in Sections 2.1 to 2.3 (DRIVE–CLiQ
wiring, connecting the Control Unit to a PC/PG via PROFIBUS, STARTER on
PC/PG), you can start commissioning using the example provided.
STARTER offers two alternative methods for creating a drive project:
S OFFLINE: you use a Wizard to configure and parameterize the drive unit.
S ONLINE: you use a Wizard to load the existing drive unit configuration and
parameterization to STARTER.
If you have created or loaded a project in STARTER, you can operate the drive via
the STARTER control panel.
Sections 2.4.1 to 2.4.3 contain tables listing the main commissioning steps for this
example. For detailed descriptions, see Chapters 3 to 5.
2.4.1

Creating the drive project OFFLINE

To create the drive project OFFLINE, carry out the following steps:
Table 2-1
Step
1
2
3
4
5
6
2-28
OFFLINE
Start the STARTER commissioning tool and use the
STARTER project Wizard to create a new project.
Set up the PROFIBUS interface.
Insert the drive unit.
Use the Wizard to configure the drive unit with, for
example, the infeed, drive properties, drive with
power section, motor, encoder, and so on.
Save the project.
Continue with "Using the STARTER control panel (motor
rotates)".
SINAMICS S120 Getting Started with the STARTER Commissioning Tool – 03/2006 Edition