Wall Mount the XN120 system

2
Remove the sub cover of the
expansion unit.
Hook the unit onto the wall
mount screws.
Tighten the lower screws to
secure the unit to the wall.
3
Earth the XN120 system.
Caution: If this cable is not
installed or requires
disconnection, then the
telecommunication network
connection(s), CO and/or
ISDN, must be disconnected
first from the XN120.
10
Push
Fasten lower
two screws
Important. Each unit must have a permanent Earth Ground
connection to a verified Earth point using a minimum of 2.5mm
green/yellow cable.
The Earth connection must have no other purpose than connecting to
the XN120 expansion unit.
Slide
Hook
onto
screws
2
The Earth point is located
on the left side under the
sub cover of each unit.