Verifying the Installation

When power is applied to the switch, power-on self-tests are run.
You can verify proper operation of the BayStack 350 switch by observing the
front-panel LEDs or by viewing the self-test results as displayed in the BayStack
350 switch Self-Test screen.
304376-B Rev 00
100-240V
47-63Hz~
BayStack 350 Switch AC Power Receptacle
Plug the other end of the AC power cord into the grounded AC power
outlet
(Figure
2-8).
612FA
Grounded AC Power Outlet
Proceed to the next section,