6.

Installation of the outdoor unit

The outdoor unit must be installed on a raised and leveled concrete slab, or on a metal rack, with a
height above ground of 100 mm.
Note:
Make sure slotted rubber pads are installed under the outdoor unit supports, otherwise vibrations
might occur, and might be transmitted, with noise, into the building.
6.1

Installation on a concrete slab

6.2

Installation on the wall

Anchor the rack to the wall by means of 1/2" diameter bolt - on studs with washers on the
wall's inner side.
Make sure that the rack is level.
Use only racks that were hot galvanized and are of appropriate strength, to carry the unit's
weight - according to the Israeli standard, part 4.
Position the outdoor unit on ribbed rubber pads supplied with the unit.
Fig. 16. Installing the outdoor unit on a concrete slab
Fig. 17. Installing the outdoor unit on a rack frame
English 16
CONTENT
1. Outside the building
2. Outdoor unit
3. Rubber padding under legs
4. Floor
5. Concrete slab
6. Anchoring screws
7. Building

Hide quick links: