Gas Valve Assembly - elco VECTRON G 05.700 MODULO Operating Instructions Manual

Table of Contents

Advertisement

Assembly

Gas valve assembly

1
3
2
7
09/2005 - Art. Nr. 13 019 526A
Assembly Gas valve assembly
· Press the gas throttle module 5 against
4
5
6
· Secure gas valve 2 so that the
· Fit the supplied gas pressure tube 7
· If available, secure external filter 1.
· Note the direction of the flow.
· Fit a thermally triggered safety valve
m
Caption
1
2
3
4
5
6
7
the burner head and tighten the 4
nuts. Then secure the gas connection
pipe 3 to the gas throttle module.
Check that O-Ring 6 and flat gasket 4
are in the correct position.
solenoids of DMV SE are positioned
vertically over the gas valve.
between the gas throttle module and
DMV SE.
and a gas ball valve (provided by
manufacturer) before the gas valve.
If the position of the gas train is
angled, use the enclosed
right-angled pressure release pipe
with screw connection.
If the gas valve is changed, the
applicable guidelines and
regulations must be observed. All
connections should be leak-tested
using foam-producing or similar
materials.
External filter
Gas valve
Gas connection pipe
Flat gasket between gas
connection pipe and gas throttle
module
Gas throttle module
O-Ring between gas throttle
module and burner head flange
Gas pressure tube
EN
15