TANK CONNECTION TO THE PIPING FRAME

General
Before moving the appliance onto the piping frame provision
must be made for the condensate drain which may be
easier before the boiler is moved into position. Refer to
Frame 19.
1. Lift tank section over the piping frame and engage the
rear of the base onto the runner of the piping frame.
Note.
At this stage if the appliance is being fitted into a cupboard
with limited access it may be advisable to attach the boiler
module on top of the tank module prior to sliding into place.
If so refer to Frame 25 for attaching the boiler module.
(Note that the CH flow pipe is supplied strapped to the
cylinder module frame).
2. Slide the tank backward until the stops on the frame are
reached.
3. Remove the pipe nut protector from the cylinder module
pipe nuts.
4. The pipes can now be connected to the piping frame
once the transit bracket is removed (see illustration).

24 BOILER MODULE PACKAGING AND REMOVAL

1. Ensure the boiler module is stood correctly as marked
on the carton.
2. Remove the strapping.
3. Fold back the top flaps and remove the top protector/
mounting template.
4. Lift off the packaging sleeve and corner protection and
discard.
5. Unscrew the 2 - M4 x 10 screws securing the front panel
and remove to one side to avoid damage.
6. Remove the controls fascia box and store to one side to
avoid damage.
24
INSTALLATION
ist8992
Top protector/
Mounting template
istor system store -
Installation and Servicing
1
Runners

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Istor he325

Table of Contents