System Balancing; Water Treatment; Boiler Assembly Exploded View - Legend For Frames 10 & 11 - IDEAL istor HE260 Installation And Servicing

Hide thumbs Also See for istor HE260:
Table of Contents

Advertisement

7

SYSTEM BALANCING

BALANCING
1. Set the programmer CH Channel to ON.
Close the manual or thermostatic valves on all radiators,
leaving the twin lockshield valves (on the radiators referred
to above) in the OPEN position.
Turn up the room thermostat and adjust these lockshield
valves to give boiler flow and return temperatures not more
o
than 20
C apart.
8

WATER TREATMENT

The istor boiler has an ALUMINIUM alloy heat exchanger
IMPORTANT.
The application of any other treatment to this
product may render the guarantee of Ideal Stelrad
Group invalid.
Ideal Stelrad Group recommend Water Treatment in
accordance with the Benchmark Guidance Notes on
Water Treatment in Central Heating Systems. Ideal
Stelrad Group recommend only the use of
or MB1, GE BETZ SENTINEL X100
Guard inhibitors and associated water treatment products,
which must be used in accordance with the
manufacturers' instructions.
Domestic Hot water
In hard water areas where main water can exceed
200ppm Total Hardness (as defined by BS 7593:2006
Table 2) a scale reducing device should be fitted into the
boiler cold supply within the requirements of the local
water company. The use of artificially softened water,
however, is not permitted.
Ideal Stelrad Group recommend the use of Fernox
Qantomat, GE Betz Sentinel Combiguard and Calmag
CalPhos I scale reducing devices, which must be used in
accordance with the manufacturers' instructions.
For further information contact:
9
BOILER ASSEMBLY - Exploded View - Legend for Frames 10 & 11
1.
Case sealing panel.
2.
Sump cover plate.
3.
Flue sensing nipple.
5.
Flue manifold kit.
6.
Flue manifold fixing.
7.
Burner
8.
Combustion chamber
insulation.
9.
Heat engine.
10.
Injector & housing.
11.
Venturi kit.
12.
Fan assembly.
13.
Gas valve inlet pipe.
14.
Auto air vent.
15.
Gas cock.
16.
Gas valve.
17.
Fan fixing kit.
18.
Orifice plate kit.
20.
Thermistor (control/return)
istor system store condensing -
GENERAL
FERNOX-COPAL
or Salamander Corrosion
21.
Overheat thermostat.
22.
Ignition electrode.
23.
Flame detection electrode.
27.
Condensate 'S' trap.
29.
User controls.
33.
Mains switch
34.
Spark generator.
34a.
Ignition lead.
37.
Prepiping frame.
45.
Turret gasket kit.
55.
Lower tundish Pipe.
56.
DHW outlet Pipe.
59.
Cold in pipe.
61.
CH flow pipe.
66.
Mains gas pipe.
67.
Pressure relief valve pipe.
70.
Tank pipe.
73.
CH return assembly.
74.
CH flow assembly.
Installation and Servicing
These valves should now be left as set.
2. Open all manual or thermostatic radiator valves and
adjust the lockshield valves on the remaining radiators,
o
to give around 15
C temperature drop at each radiator.
3. Adjust the room thermostat and programmer to NORMAL
settings.
Fernox Manufacturing Co. Ltd.
Cookson Electronics
Forsyth Road
Sheerwater Woking
Surrey GU21 5RZ
+44 (0) 1799 521133
Salamander Engineering Ltd
The Heath Business &
Technical Park,
Runcorn,
Cheshire, WA7 4QX
Tel: +44 (0) 121 3780952
Notes.
1. It is most important that the correct concentration of the
water treatment product is maintained in accordance with
the manufacturers' instructions.
2. If the boiler is installed in an existing system any
unsuitable additives MUST be removed by thorough
cleansing. BS. 7593:2006 details the steps necessary to
clean a domestic central heating system.
3. In hard water areas, treatment to prevent lime scale may
be necessary - however, the use of artificially softened
water is NOT permitted.
4. Under no circumstances should the boiler be fired before
the system has been thoroughly flushed.
77.
Tank flow pipe (Top).
81.
DHW expansion vessel.
82.
CH expansion vessel.
83.
Pump.
85.
Divertor valve.
89.
Thermostatic mixing valve.
90.
Temp & pressure relief valve.
91.
CH Pressure relief valve.
92.
DHW Pressure relief valve.
93.
Tundish assy.
95.
Filling loop.
101.
Pressure gauge.
102.
Fascia controls assy.
103.
Dry fire thermistor.
Sentinel Performance Solutions
The Heath Business &
Technical Park, Runcorn,
Cheshire, WA7 4QX
Tel. 0800 389 4670
www.sentinel-solutions.net
Calmag Ltd.
Unit 4-6, Crown Works
Bradford Road
Sandbeds, Keighley